Framing costs and how to hire a framing contractor.
Written from 20+ years of framing commercial, multi-family, and custom residential projects along the Colorado Front Range. No sales pitch — just what actually drives the price, the schedule, and the difference between a good framer and an expensive one.
What a framing contractor actually does
Framing is the structural skeleton of a building — the floor system, the walls, the roof structure. Everything after framing depends on it being square, plumb, and built to the engineered plans. When framing is off, drywall, cabinets, windows, and finish trades all pay for it later.
A framing contractor reads the structural plan set, orders and manages the lumber and hardware for that scope, and builds the structure in the sequence the rest of the job needs. On larger jobs the framer also coordinates phasing with the general contractor so following trades never sit waiting.
What drives the cost of framing
There is no honest per-square-foot number that works for every project, because the same square footage can cost very different amounts. These are the factors that move the number most:
- Square footage and number of stories — more area and more floors mean more structure and more labor.
- Complexity of the design — simple gable rooflines cost less to frame than vaulted ceilings, dormers, and cut-up plans.
- Materials specified — engineered lumber, larger members, and specialty hardware carry higher material costs.
- Site conditions and access — tight urban sites, occupied buildings, and difficult access slow the work down.
- Remodel vs new construction — tying into an existing structure takes more care and uncovers more surprises than building new.
- Schedule requirements — compressed schedules or phased work across multiple buildings change how crews are staffed.
This is why we quote from plans rather than over the phone. Send us the set, or describe the work, and we come back with a detailed estimate for your actual scope.
How long framing takes
A single-family remodel or addition can be framed in days to a few weeks. Custom homes generally run a few weeks. Multi-family and commercial buildings are framed in phases over weeks or months, building by building.
The schedule matters as much as the price. When we quote a project we include a realistic framing schedule and coordinate it with the general contractor, so framing hands off clean instead of becoming the bottleneck.
What to ask before you hire a framing contractor
Framing is one of the trades where the cheapest bid frequently costs the most. Before you award the scope, ask:
- Are you licensed and insured, and can I see proof? (We provide ours with the quote.)
- Have you framed this building type before — commercial, multi-family, custom residential? Ask for named projects.
- Who is actually on site? Is it your own crew, or subcontracted out?
- How do you handle change orders and surprises — do I approve cost changes in writing first?
- What framing schedule are you committing to, and how do you coordinate with the other trades?
- Is the bid complete, or are there scope items excluded that I'll be asked to pay for later?
A framer who answers those clearly, in writing, is usually the one who will not blow up your schedule.
How changes should be handled
Plans get revised, and framing uncovers things nobody expected — especially in remodels. That is normal. What matters is how it is handled.
Our rule is simple: we flag it right away, explain the options and the cost impact, and get written approval before we proceed. You should never find work on an invoice you did not sign off on. If a contractor cannot describe their change process, treat that as a warning.